Reopen Rate Over Time(JIRA:1.3.5)

Visual

Every reopen records a ticket that came back after it was marked done. A reopen is a move out of a status your organization classifies as delivered (a MetaFrazo default applies until configured) back into a To Do or In Progress status; an issue revived out of a status classified as abandoned is not a reopen. This visual tracks the weekly rhythm of completions against reopens, and shows you the weekly reopen rate so you can see at a glance whether the rate is rising or falling.

A single reopen here and there moves the rate little. A consistently high rate, or one that is climbing week over week, raises questions about requirements, handovers, testing gates, or acceptance criteria.

What you can conclude

  • A rising reopen rate over multiple weeks means the reopens are not confined to one week; the question is what changed in how work is defined or accepted.
  • For spikes in specific weeks, a reviewer could ask whether they line up with sprint ends or deadlines, and whether the reopened tickets were closed before their work was finished.
  • A declining rate over time means fewer completed tickets are being reopened; the chart does not show why.

How this chart works

Line chart showing the weekly reopen rate (%) over time. A completion is an issue moved into a status classified as delivered, counted once per project and week; a closure into an abandoned status is not a completion. Each point represents one week; point size reflects the number of completions that week, so larger points are statistically more reliable than smaller ones. A week's rate can exceed 100%, because it divides the reopens recorded in that week by the completions recorded in the same week, and a ticket reopened this week may have been completed in an earlier one. Points above the 20% review threshold are shown in coral; points below are shown in teal.

A dashed reference line marks the 20% threshold referenced in the What you can conclude section.

Use the date and project filters to focus on a specific period or team.

The week in progress is shown at its rate so far. Because the week is not yet complete, it covers only the completions and reopens recorded so far and can move in either direction as the week closes. Deep Analysis reads only the complete weeks and leaves the week in progress out.

How far back it reads

The chart reads at most the last 92 days, a calendar quarter, of the selected range, ending on the range's last day or today, whichever is earlier. A range that starts within those 92 days is read whole. For a longer range, or one with no start date, it draws the weeks of those 92 days, and the panel says so beside its title. To review an earlier period, end the range there. This keeps the read within the panel's row limit however many projects the organization adds.