Portfolio Workflow Anomaly Heatmap, Project × Week(JIRA:2.1.11)

Visual

This is the executive summary view. Instead of reading the bypass and reopen signals project by project, the anomaly heatmap shows both at once: project by project, week by week, in a single color-coded grid, for at most twelve projects by name (see below).

A dark red cell means that project scored 75 or above that week. A white cell means its score sat below 25. The trend arrows show whether each score rose or fell week over week. One glance replaces a manual weekly portfolio review.

What you can conclude

  • A whole row of dark cells (one project across many weeks) shows a project scoring high week after week rather than in a single week.
  • A whole column of dark cells (all projects in one week) shows every project scoring high in the same week; ask whether a deployment or a process change falls in that week.
  • Cells moving from red toward white across recent weeks show the scores falling; the chart does not show why.

How this chart works

Heatmap with projects on one axis and weeks on the other. Each cell shows a transition deviation score from 0 to 100 built from two measures of that project's status transitions in that week: bypasses (a transition from a not-started status straight into a done one) and reopens (a transition from a status classified as delivered back to a To Do or In Progress status; a revival out of a status classified as abandoned is not a reopen). Bypasses weigh 0.35 and reopens 0.30, the weighted sum is divided by the week's total status transitions, and the result is scaled so that a week made up entirely of bypasses scores 100. Project Risk Ranking JIRA:3.2.8 ranks projects on a transition deviation score that weighs a reopen slightly less, 25 against 30 for a bypass, so a project's figure for the same week can differ between the two panels, most in a week with many reopens. A week with fewer than 10 status transitions is not scored and shows n/a; a project with no status transitions in a week has no cell to score and shows a dash; a measured 0 is drawn as 0. Each cell is colored by the range its score falls in: below 25 (white), 25 to under 50, 50 to under 75, and 75 and above (red, darkest from 90). Each cell prints its score to one decimal, the precision its range is decided on. Trend arrows show week-over-week direction per cell.

The week in progress is shown at its value so far. Because the week is not yet complete, it is marked as still in progress and does not enter the trend comparison. Deep Analysis reads only the complete weeks and leaves the week in progress out.

How far back it reads

The heatmap reads at most the last 92 days, a calendar quarter, of the selected range, ending on the range's last day or today, whichever is earlier. A range that starts within those 92 days is read whole. For a longer range, or one with no start date, it draws the weeks of those 92 days, and the panel says so beside its title. To review an earlier period, end the range there. This keeps the read within the panel's row limit however many projects the organization adds.

Which projects are drawn

With no project picked, the heatmap draws a row for at most twelve projects: of the projects with at least 2 scored complete weeks shown (1 when the range holds a single complete week), the twelve with the highest average transition deviation score, each project's scored weeks averaged and its unscored weeks left out. Ties go to the project key that sorts first, and the week in progress is drawn but counts toward neither the choice nor the 2 weeks. An average of one week is that week alone, so a project with fewer scored weeks is always in the Other projects row. A score does not add up across projects, so every other project is drawn as one gray Other projects row: each week, the median score of the other projects scored that week, each project counting once whatever its volume, rounded to one decimal like the scores. Its cells are gray rather than colored by range and carry no trend arrow, because the median is not a project's score; a week where none of them could be scored shows n/a, and a week where none of them had a status transition shows a dash. A dark column is read across the twelve projects drawn, and the Other projects row shows where the rest sat that week. Pick a project in the filter to see its own row at any time; with twelve or fewer projects at or above 2 scored weeks every one of them is drawn, and the Other projects row appears only when some project has fewer.