Reopen Surge Detector(JIRA:2.1.8)
VisualA stable reopen count, even a high one, describes a steady state. A reopen count that is growing week over week moves before sprint metrics do, because a reopen is recorded when work comes back rather than when it is next planned. This detector measures the acceleration of reopens, not just the count, so a rising trend shows early.
A project whose weekly reopen count doubled in two weeks reads differently from one that has reopened about the same number of issues every week for months. This visual shows you the trajectory, not just the position.
What you can conclude
- A week-over-week increase of more than 50% in any project is rated a surge.
- When multiple projects accelerate simultaneously, ask whether a recent deployment or process change came first.
- A project whose weekly count is stable, even if high, is reopening work at a steady pace.
How this chart works
Multi-series line chart of reopens per calendar week, one line per project. Each point is the number of reopens recorded in that week, a reopen being a status change from a status your organization classifies as delivered (a MetaFrazo default applies until configured) back to a To Do or In Progress status; an issue revived out of a status classified as abandoned is not a reopen. Each complete week is also rated against the week before it from the percentage change in that count, not from the absolute count: surge when the count rose by more than 50 percent, increasing above 10 percent, decelerating when it fell, stable otherwise. A week whose previous week had no reopens is not rated, because there is no base for a percentage. The rating is not drawn on the chart; it is published beside each week's count and is available to Deep Analysis.
The week in progress is shown at its raw count so far. Because the week is not yet complete, it carries no week-over-week change. It is not rated while it is open.
How far back it reads
The chart reads at most the last 92 days, a calendar quarter, of the selected range, ending on the range's last day or today, whichever is earlier. A range that starts within those 92 days is read whole. For a longer range, or one with no start date, it draws the weeks of those 92 days, and the panel says so beside its title. To review an earlier period, end the range there. This keeps the read within the panel's row limit however many projects the organization adds.
Which projects are drawn
With no project picked, the chart draws a line for at most twelve projects: the twelve with the most reopens over the complete weeks it shows. Ties go to the project key that sorts first, and the week in progress is drawn but does not count toward the choice. Reopens add up, so every other project is added into one gray Other projects line, and in any week the lines still add up to the reopens of every project read. The Other projects line is not rated, because a rating compares one project's week with its own week before. Pick a project in the filter to see its own line at any time; with twelve projects or fewer every project is drawn and there is no Other projects line.