Delivery Forecast(JIRA:1.1.16)

Visual

A Monte Carlo forecast runs a project's recent delivery history forward many times and reports the spread of the outcomes. This visual answers two questions: how many work items could be delivered by a chosen date, and by which date a chosen number of work items could be delivered. Each answer is a range of outcomes, not a promise: every figure says how often recent throughput, replayed at random, reached it.

Questions this can help answer

  • If the coming weeks look like the recent ones, how many work items could this project deliver by the end of the month?
  • By when could the next 40 work items be delivered, and how wide is that range?
  • How much does the range widen as the date moves further out?

How this forecast works

The sample is the number of work items delivered on each day of the window, zeros included: a day with no delivery is a measured zero and stays in the sample. A work item counts once, on the day it first moves into a status your organization classifies as delivered under its terminal-status settings (a MetaFrazo default applies until configured), the same count Throughput Distribution uses. The forecast draws one past day at random for each future day, counting from today, and adds up the work items those days delivered. Today counts as the first future day, and what has already been delivered today is not subtracted. Days are drawn without regard to the weekday, so a forecast over one or two days reads an average day, weekends included. It repeats this 10,000 times from a fixed starting seed, so the same history always gives the same figures.

The panel reports four confidence levels: 50, 70, 85 and 95 %. For "how many by a date", the figure at 85 % is the number of work items that 85 % of the runs reached or exceeded, so a higher level names fewer work items. For "by when", the date at 85 % is the day by which 85 % of the runs had delivered the chosen number, so a higher level names a later date. A run that has not delivered the chosen number within two years names no date.

The forecast assumes the coming days resemble the sampled ones. It knows nothing about planned work, holidays, team changes or work items not yet created, so it describes what recent throughput would produce if it continued.

The week in progress is not counted: only complete weeks enter the sample the forecast draws from. Weeks run Monday to Sunday (UTC). A week before MetaFrazo first recorded a work item of the project is not counted either, so the history starts no earlier than the day the app was installed.

With no project selected, the forecast counts every project together; with a project selected, it counts that project alone. An organization with more than one connected Jira site gets one forecast per site, and sites are never added together.

History window and minimum

The window is the last 8, 13 or 26 complete weeks, ending with the last complete week, and the panel states its dates. The page's date range does not move it. With fewer than 8 complete weeks recorded in the window, the panel shows "not enough history" instead of a forecast. When no work item was delivered in the window, the panel shows no forecast, because a history without deliveries cannot be run forward.

What Deep Analysis reads

Deep Analysis reads the figures the page computed: the question asked, the chosen date or number of work items, the figure at each confidence level, and the window's dates, complete weeks, days with no delivery and work items delivered.