Net Backlog Change(JIRA:3.3.2)
KPINet change in backlog size in the latest complete week—positive means the backlog is growing, negative means shrinking. The single number for whether arrivals or closures led that week. This card reads the latest complete week and names the week it read. The week in progress is left out rather than counted: new issues are recorded the moment they arrive while closures accumulate across the week, so a part-finished week overstates backlog growth every week of the year rather than only sometimes. If the only week in the selected range is still in progress, no number is shown. The chart below still plots the week in progress. Every move into a status of Jira's Done category counts as leaving the backlog, whether the work was delivered or abandoned. The resolved count on Backlog Net Growth Trajectory JIRA:3.3.6 shows delivered work only, so it can be smaller than the closures counted here.